Topics
- Map of improvements
- Construction plan
- Community sensitive design
- Community outreach
- Traffic management
- Workforce development
- Work zone safety
- Project history
Select the topics below to learn about the I-94 North-South Freeway Project. Use the "Help" link located to the left for detailed information about the tools on this Web site. Some items require Adobe Reader or Windows Media Player.
The Plainfield Curve (I-43/94 near Howard Avenue) was reconstructed to a smoother, single curve to improve safety of traffic. This new curve is designed to accommodate speeds up to 55 mph. The Plainfield Curve was completed in Fall 2012.
The 27th Street Interchange was reconstructed with U-ramps to significantly improve traffic flow and safety. All traffic is now entering the freeway via right-hand turns and eliminates vehicles turning left and crossing 27th Street to access the freeway. The interchange was completed in Fall 2012.
The Mitchell Interchange was reconstructed to have all traffic entering and exiting from the right. This design has eliminated confusion and improved safety. One of the more significant changes is the rerouting of maneuvers to and from 27th Street and I-94 South. Traffic on 27th Street will utilize the I-94 EAST (SB) entrance ramp from Layton Avenue to access I-94. Three tunnels were included in the design (one tunnel from I-94 WEST (NB) to I-43/894 west and two tunnels from I-43/894 east to I-43/94 north). The Mitchell Interchange was completed in Fall 2012.
The Layton Avenue Interchange was reconstructed into a diamond configuration which will improve traffic operations on Layton Avenue. New traffic signals at the NB and SB ramp terminations were installed. The I-94 EAST (SB) entrance ramp from 20th Street was relocated to Layton Avenue. The interchange was completed in Fall 2012.
The Airport Spur was reconstructed in its existing configuration. The newly constructed Spur looks like a parkway and has a field stone wall located in the median. The outside edges have a screening berm with landscaping. The interchange and ramps were completed in Fall 2012.
The College Avenue Interchange was reconstructed to a tight diamond interchange. The ramp connections were brought in closer to I-94 which allows more space for the adjacent cross streets and improved traffic operations. The park and ride lots in the NE and SW quadrants were also reconstructed. The interchange was completed in 2009.
The Rawson Avenue interchange will be reconstructed to a tight diamond interchange. This means that ramp connections with the cross street will be brought closer to I-94. Doing this allows more space between the ramp and the adjacent cross streets – 13th Street and 20th Street, for better traffic operations.
The interchange construction is scheduled to be completed in Fall 2013.
The Drexel Avenue Interchange is a new interchange added to the I-94 North-South Corridor between Rawson Avenue and Ryan Road. The interchange is a tight diamond configuration where the ramps are close to I-94 for improved traffic operations. The interchange was completed in Fall 2012.
The Ryan Road interchange will be reconstructed to a tight diamond interchange. This means that ramp connections with the cross street will be brought closer to I-94. Doing this allows more space between the ramp and the adjacent cross streets – 13th Street and 20th Street, for better traffic operations.
The Ryan Road Interchange will begin in Spring 2014 and is scheduled to be completed in Fall 2014.
The existing interchange at 27th Street and I-94 will be reconstructed from a half diamond interchange to a full diamond interchange. This interchange will be moved approximately a half mile further north to avoid impacts to the Root River environmental corridor and will improve spacing with the Seven Mile Road interchange. It will be built with a connection to 27th Street.
The Elm Road Interchange and mainline are tentatively scheduled to be constructed in 2017.
The existing crisscrossing ramp/frontage road configuration at 7 Mile Road will be reconstructed to eliminate the unsafe movements. The entrance/exit ramps will be configured as a diamond interchange. The east frontage road will be routed around current businesses and residences that are adjacent to the existing frontage road. The west frontage road will be routed west of 7 Mile Fair. Storm water detention ponds are planned for the NE and SE quadrants of the interchange.
The 7 Mile Road Interchange and mainline are tentatively scheduled to be reconstructed in 2019.
The County G Interchange was reconstructed to eliminate the existing unsafe scissor ramps and reconstructed as a diamond interchange. The interchange and mainline was completed in 2009.
The existing crisscrossing ramp/frontage road configuration at County K will be reconstructed to eliminate the unsafe movements. The entrance/exit ramps will be configured as a diamond interchange. The east and west frontage roads will be routed around current businesses and residences adjacent to the existing frontage road. Storm water detention ponds are planned for the NE, NW and SW quadrants of the interchange.
The County K Interchange and mainline are tentatively scheduled to be reconstructed in 2021.
The entrance/exit ramps will be configured as a diamond interchange at WIS 20. The east frontage road will be realigned north of WIS 20. The County C intersections with the east and west frontage roads (north of WIS 20) will also be reconstructed as part of this project.
The WIS 20 interchange and mainline are tentatively scheduled to be reconstructed in 2014.
The entrance/exit ramps will be constructed with a partial cloverleaf configuration, similar to the existing configuration. The east frontage road will be realigned east of its current configuration north of Old Hwy 11 and the west frontage road will be realigned west of its current configuration north of 58th Road. 58th Road between the frontage roads will also be improved as part of this project.
The WIS 11 Interchange and mainline are tentatively scheduled to be reconstructed in 2020.
The existing crisscrossing ramp/frontage road configuration at County KR will be reconstructed to eliminate those unsafe movements. The entrance/exit ramps will be configured as a diamond interchange. The east and west frontage roads will be routed around current business and residences adjacent to the existing frontage road. The stream along County KR, east of I-94, will be realigned. A storm water detention pond is planned for the SE quadrant of the interchange.
The County KR Interchange and mainline are tentatively scheduled to be reconstructed in 2018.
The existing crisscrossing ramp/frontage road configuration at County E will be reconstructed to eliminate those unsafe movements. The entrance/exit ramps will be configured as a diamond interchange. The east and west frontage roads will be routed around current business and residences adjacent to the existing frontage road. Storm water detention ponds are planned for the NE, NW and SE quadrants of the interchange.
The County E Interchange and mainline are tentatively scheduled to be reconstructed in 2016.
The existing crisscrossing ramp/frontage road configuration at WIS 142/County S will be reconstructed to eliminate those unsafe movements. The entrance/exit ramps will be configured as a diamond interchange. The east and west frontage roads will be routed around current business and residences adjacent to the existing frontage road. Flat bottomed wide ditches in SE and NW quadrants of the interchange will help with water quality.
The WIS 142/County S Interchange and mainline reconstruction began in Spring 2013 and is scheduled to be completed in Fall 2014.
The WIS 158 interchange reconstruction is part of the WIS 50-WIS 158 mainline project that began in 2012. The WIS 158 interchange is scheduled to be completed in Fall 2013.
The WIS 50 Interchange is part of the WIS 50-WIS 158 mainline project that began in 2012. The WIS 50 interchange is schedule to be competed in Fall 2013.
The County C Interchange was reconstructed to eliminate the existing unsafe scissor ramps as a tight diamond configuration. The interchange was completed in 2009.
No changes to the existing interchange configuration are planned
The interchange construction was completed in 2009; mainline construction is set to be completed in 2010. West frontage road is being worked on by others.
No changes to the existing interchange configuration are planned.
The Russell Road interchange will be reconstructed in its current configuration.
Check here for updates to designs